Nowadays, User:Tol/sandbox is a topic of great relevance in today's society. For decades, User:Tol/sandbox has been the subject of interest and debate in different areas, from politics to science. There are many aspects surrounding User:Tol/sandbox, from its origins to its global implications. In this article, we will explore some of the most relevant facets of User:Tol/sandbox, addressing its multiple dimensions and impacts today. From its influence on the economy, through its repercussions on daily life, to its relationship with other areas of knowledge, User:Tol/sandbox is presented as a topic of study and reflection of great importance to understand the current world. Along these lines, we will analyze some of the ideas and theories that have emerged around User:Tol/sandbox, as well as the perspectives and debates that remain valid today.
Tol/sandbox/tempmake space (] 1)(] 2)fill space (] 3)Uvariopsis dicaprio was described ...
Business plan: 2024 Business Plan[1]
Comprehensive status report: 2025 Project Update Report[2]
Construction update to Board: Construction Update, 19 Feb 2025[3]
Recent construction status: Central Valley Status Report, March 2025 data[4]
| #[a] | Project | Distance | Status | Completion | Notes | Refs |
|---|---|---|---|---|---|---|
| Lincoln Avenue GS | Canceled | Lincoln Ave to instead be terminated on either side of alignment. | ||||
| - | Adams Avenue GS | 199.49 mi (321.05 km) | Completed | Dec 20, 2022 | 357 ft (109 m) long, 40 ft (12 m) wide; over BNSF tracks and HSR alignment. | [5] |
| - | South Avenue GS | 200.49 mi (322.66 km) | Completed | Feb 28, 2022 | 390 ft (120 m) long, 43 ft (13 m) wide; over BNSF tracks and HSR alignment. | [6] |
| BNSF track realignment | In progress | Shifting tracks to the east side of right of way between South Ave and Conejo Viaduct. | ||||
| - | Manning Avenue GS | 201.49 mi (324.27 km) | In progress | Q1 2026 (exp.) | 342 ft (104 m) long, 43 ft (13 m) wide; over BNSF tracks and HSR alignment. As of May 2025, abutments and foundational work in progress. | [7][3]: 14 |
| - | Floral Avenue GS | 203.52 mi (327.53 km) | Completed | Jul 15, 2024 | 381 ft (116 m) long, 40 ft (12 m) wide; over BNSF tracks and HSR alignment. | [8] |
| - | Nebraska Avenue GS | 204.60 mi (329.27 km) | In progress | Q4 2026 (exp.) | 785 ft (239 m) long, 43 ft (13 m) wide; over BNSF tracks and HSR alignment. As of May 2025, embankments are complete and bridge bents are being constructed. | [9][3]: 14 |
| Elkhorn Ditch relocation | In progress | Relocation and culvert installation for canal to cross under HSR alignment. As of 2025, section of the old BNSF Railway over the canal have been removed and earthworks are being constructed. | [10] | |||
| - | Mountain View Avenue GS | 205.58 mi (330.85 km) | Completed | Jul 15, 2024 | 368 ft (112 m) long, 40 ft (12 m) wide; over BNSF tracks and HSR alignment. | |
| - | Conejo Viaduct & Pergola | 207.70 mi (334.26 km) | In progress | Q3 2025 (exp.) | 2,000 ft (610 m) long, 34 ft (10 m) wide; over BNSF tracks and Conejo Ave via a pergola. All girders have been placed. | [11][3]: 14 |
| - | Peach Avenue Viaduct | 208.29 mi (335.21 km) | Completed | Dec 6, 2024 | 306 ft (93 m) long, 43 ft (13 m) wide; over Peach Ave. | [12] |
| - | Elkhorn Avenue GS | Completed | Jul 7, 2023 | 345 ft (105 m) long, 40 ft (12 m) wide; over HSR alignment. | [13] | |
| - | Fowler Avenue GS | Completed | Dec 21, 2022 | 299 ft (91 m) long, 40 ft (12 m) wide; over HSR alignment. | [14] | |
| - | Davis Avenue Overcrossing | 212.08 mi (341.31 km) | Completed | Oct 30, 2023 | 416 ft (127 m) long, 32 ft (9.8 m) wide; over HSR alignment. | [15] |
| - | State Route 43 Tied Arch Bridge | In progress | Q3 2025 (exp.) | 249 ft (76 m) long, 52 ft (16 m) wide; over SR 43. As of June 2025, bridge deck is complete and concrete pour for the arches of the bridge will soon begin. | [16][3]: 14 | |
| - | Cole Slough Viaduct | In progress | Q2 2026 (exp.) | Right of way leading up on both sides cleared; river basin partially cleared. | [3]: 14 | |
| - | Dutch John Cut Bridge | In progress | Q1 2026 (exp.) | 669 ft (204 m) long, 43 ft (13 m) wide; over Dutch John Cut waterway. Temporary viaduct completed to allow construction of the piers of the permanent structure. | [17][3]: 14 | |
| - | 9th Avenue Viaduct | 215.67 mi (347.09 km) | Completed | 2025 | Over 9th Ave. Bridge completed; embankment appears to be finished. | [18] |
| - | Cairo Avenue Viaduct | 216.09 mi (347.76 km) | Completed | Dec 20, 2022 | 84 ft (26 m) long, 43 ft (13 m) wide; over Cairo Ave. | [19] |
| - | Kings River Viaduct | In progress | Q2 2025 (exp.) | 445 ft (136 m) long, 43 ft (13 m) wide; over Kings River. Three rows of bridge supports being built up, with northern bridge abutment completed as of October 7, 2022. Temporary construction access bridge erected over the waterway. | [20][3]: 14 | |
| - | Dover Avenue Overcrossing | 217.82 mi (350.55 km) | Completed | May 3, 2023 | 227 ft (69 m) long, 43 ft (13 m) wide; over HSR alignment. | [21] |
| - | Excelsior Avenue GS | 218.30 mi (351.32 km) | In progress | Over HSR alignment. Bridge deck completed. Embankments were started but stopped, possibly due to utility issues. | [22] | |
| Elder Avenue GS | Canceled | Elder Ave to instead be terminated on either side of alignment. | ||||
| - | Flint Avenue GS | 220.86 mi (355.44 km) | Completed | Jun 26, 2024 | 205 ft (62 m) long, 40 ft (12 m) wide; over HSR alignment. | [23] |
| - | Fargo Avenue GS | 221.88 mi (357.08 km) | Completed | Jan 30, 2025 | 205 ft (62 m) long, 40 ft (12 m) wide; over HSR alignment. | [24] |
| - | Grangeville Boulevard Viaduct | In progress | Q4 2026 (exp.) | Connecting between ground level and the Hanford Viaduct. | [25][3]: 14 | |
| - | Hanford Viaduct | In progress | Q4 2025 (exp.) | 6,330 ft (1,930 m) long; over Grangeville Blvd, SJVR, and SR 198. All 286 bridge columns completed. Construction of falsework for the superstructure is underway. As of June 2025, only one section of 978 total girders needed appears to remain; majority of the deck has been poured, with some areas already having barriers poured as well. | ||
| - | Hanford Armona Road GS | 224.92 mi (361.97 km) | In progress | Q4 2025 (exp.) | Embankments have been built up; waiting for bridge construction to begin. | [3]: 14 |
| - | Houston Avenue GS | 225.96 mi (363.65 km) | In progress | Q4 2026 (exp.) | Over HSR alignment. Dirt moving has begun. | [3]: 14 |
| Iona Avenue GS | Not yet started | Unknown if to be constructed. If not, Iona Ave to be terminated on either side of alignment. | ||||
| - | Idaho Avenue Overcrossing | 227.96 mi (366.87 km) | Completed | May 3, 2023 | 205 ft (62 m) long, 40 ft (12 m) wide; over HSR alignment. | [26] |
| - | Jackson Avenue Overcrossing | 228.97 mi (368.49 km) | Completed | Sep 15, 2022 | 212 ft (65 m) long, 35 ft (11 m) wide; over HSR alignment. First structure completed in Kings County. | [27] |
| - | State Route 43 Overpass at Jersey | In progress | Q1 2026 (exp.) | HSR alignment to pass through a closed Jersey Ave and under SR 43, which will be rebuilt on an elevated structure. Road temporarily realigned west in mid-November 2023. As of June 2025, embankments and bridge piers are complete; deck work in progress. | [3]: 14 | |
| - | Kent Avenue GS | 231.18 mi (372.05 km) | Completed | Oct 12, 2022 | 215 ft (66 m) long, 35 ft (11 m) wide; over HSR alignment. | [28] |
| - | Kansas Avenue GS | 232.21 mi (373.71 km) | Completed | Nov 2, 2023 | 207 ft (63 m) long, 43 ft (13 m) wide; over HSR alignment. | [29] |
| - | Lansing Avenue Underpass | Not yet started | Q3 2025 (exp.) | Box culvert-style agricultural underpass. | [3]: 14 | |
| - | Cross Creek Viaduct | In progress | Q2 2025 (exp.) | 2,500 ft (760 m) long, 43 ft (13 m) wide; over Cross Creek. | [30][3]: 14 | |
| - | State Route 43 Curved Bridge | 235.82 mi (379.52 km) | In progress | Q2 2026 (exp.) | 660 ft (200 m) long, 45 ft (14 m) wide; over SR 43. As of June 2025, embankments are completed and bridge bents are being constructed. | [31][3]: 14 |
| Nevada Avenue & Highline Canal culvert | Completed | 2025 | New culvert and realignment of adjacent canal. Nevada Ave will be terminated on either side of the HSR alignment. | |||
| Newark Avenue Overpass | Not yet started | Over Newark Ave. May not be built, in which case Newark Ave will be terminated on either side of the HSR embankment. | ||||
| Sweet Canal Relocation | Completed | 2025 | Relocation and culvert installation for Sweet Canal to cross under HSR alignment. | |||
| - | Waukena Avenue Overpass[b] | 240.17 mi (386.52 km) | In progress | Q3 2026 (exp.) | Over a realigned Waukena Ave (Corcoran Hwy). As of June 2025, columns for bridge piers and embankment work are under construction. | [3]: 14 |
| - | Whitley Avenue Underpass | 241.16 mi (388.11 km) | Completed | Apr 24, 2025 | 128 ft (39 m) wide; over Whitley Ave (SR 137). | [32] |
| - | Avenue 156 GS | 241.16 mi (388.11 km) | In progress | Q3 2025 (exp.) | Over Ave 156. Construction started in 2024. | [3]: 14 |
| - | Tule River Viaduct & Pergola | 244.79 mi (393.95 km) | In progress | Q4 2025 (exp.) | 3,573 ft (1,089 m) long; over SR 43 (realigned), Ave 144 (Poplar Ave), BNSF tracks (via a pergola), and the Tule River. As of May 2025, all pre-cast girders have been placed at the pergola section; deck work is in progress. As of June 2025, retaining wall work is being constructed more on the south embankment. | [33][3]: 14 |
| - | Avenue 136 GS | Not yet started | Q3 2025 (exp.) | [3]: 14 | ||
| - | Avenue 120 GS | 248.10 mi (399.28 km) | In progress | Q3 2026 (exp.) | As of June 2025, embankments are being built up, after which bridge construction can begin. | [3]: 14 |
| - | Lakeland Bridge | In progress | Q1 2026 (exp.) | 402 ft (123 m) long, 43 ft (13 m) wide; over the relocated Lakeland/Homeland Canal. | [34][3]: 14 | |
| - | Avenue 88 GS | 252.90 mi (407.00 km) | In progress | 485 ft (148 m) long; over SR 43, BNSF tracks, and HSR alignment. Embankments and abutments complete. Bridge deck complete; awaiting paving of embankment ramps. | [35] | |
| - | Deer Creek Viaduct | In progress | Q4 2025 (exp.) | 3,000 ft (910 m) long, 43 ft (13 m) wide; Deer Creek and adjacent wetlands to its south. As of June 2025, most bridge piers and girders have been constructed and some deck work is underway. | [36][3]: 14 | |
| - | Stoil Spur Underpass | In progress | Q1 2026 (exp.) | HSR to cross over West Isle Line railroad on an overhead structure. As of June 2025, embankment works are being constructed. | [3]: 14 | |
| - | Alpaugh Bridge | In progress | Q1 2026 (exp.) | Viaduct spanning part of Alpaugh Pond. As of June 2025, embankment works are being constructed. | [3]: 14 | |
| - | Avenue 56 GS | 257.16 mi (413.86 km) | Completed | Jun 16, 2025 | 219 ft (67 m) long, 35 ft (11 m) wide; over HSR alignment. First structure completed in Tulare County. | [37][38] |
| Avenue 44 Agricultural Crossing | In progress | Small box culvert-style agricultural underpass. As of June 2025, structure looks just about complete with embankment works needed to be constructed. | ||||
| - | Avenue 24 GS | 261.17 mi (420.31 km) | In progress | Box culvert-style agricultural underpass. Utility relocations complete. As of June 2025, structure appears to be completed while embankments are being constructed. | ||
| ? | AAAT[c] Underpass | Completed | May 2024 | Location unknown. | ||
| ? | Access Road Underpass | In progress | Q1 2026 (exp.) | Location unknown. | [3]: 14 |